Weather: Very Windy
Temperature: 75 degrees
Work Completed Today: Finished forms on Tunnel #3 (1st half) of invert. Set forms for walls on collection tunnel. Excavated more on mud slab for tunnel #2.
Visitors: Marco from Italy
Forming the break in the floor.
working on the trough in tunnel #1
Excavating the mud slab again on tunnel #2.