Daily Project Report
Weather: Sunny/windy
Temperature: 80
Work Completed Today: Added splice rebars as requested by SOCOTEC. Formed Block outs for expansion/shrinkage as requested by SOCOTEC. Shot elevations. Prepared all for Monday's 6:00 a.m. pour. Informed Betomar that their price was too high. Talked to Talbi and Chafiq about price. They agreed to talk to Zenjari to see if we could get a better price. Received through our office the go ahead on the arch tunnels. Talked to people in Casablanca about Rebar. Waiting for a written bid. Will place order on Monday.
Talked with office/Project manager.
Equipment: Renewed Rental Car Contract
Other Notes: Provided local law enforcement (public safety) with list of workers.

The start of the day.
Working on details.
Blocking up the sump pit forms.

Everyone was glad we had Cody on the job for this one.


Fabricating more rebar.