Tuesday, May 20, 2008

Tuesday May 20, 2008

Daily Project Report
Weather: Windy
Temperature: 82
Work Completed Today: Tied floor steel in Arch tunnel #1. Tied floor steel in Arch tunnel #3. Taught some of the Blue Men how to use twisters. Finally found some concrete pavers that we could use for dobies. Made chairs for floor steel. Tied steel in pit walls. Finally got rebar bid.
Did not talk to Project Manager/Office Today
Materials Delivered: Dobies
Visitors: ICG

I did not have any pictures from today, so I decided to show you what the trucks have to do to navigate getting in and out of the excavation.


No comments: