Daily Project Report
Weather: Warm and Sunny
Temperature: 80+ Degrees F.
Work Completed Today:
Built wood forms for tunnel inverts. Cut invert rebar. Finished organizing the tool crib. Built shade shelter. Shot elevations and set grade stakes. Set forms for pit mud slab. Dug sump pit & invert of pit. It is a national holiday today - Labor Day. Checked out and fired up big generator.

Building the forms.
Cutting rebar.
Making new calculations.


Organization at last.