Daily Project ReportWeather: Windy/sand
Temperature: 85 degrees
Work Completed Today:
4 new locals started today making our Blue Man Crew 12. Tied steel in pit walls. Tied steel in invert for tunnel #1. Excavated on center tunnel. Cleaned up debris from pit invert pour. Poured mud slab for arch tunnel #3.
Did you talk with Office/ project manager today?: Yes
Owner/Engineer directives provided: Yes
Equipment delivered: Forklift
Visitors: Mr.s Chafiq and Talbi

The site that greeted us first thing this morning was around twenty men wanting a job.

The pictures aren't in any certain order. We have Jeff making chairs, Darryl and help making dobies, Luis setting chairs,
Cleaning up dibris, tying steel, a photographer and videographer filming the work.


Cindy making chairs and the guys starting the pour. Comparing the two fresh pours. The one in the top corner was poured an hour earlier and is covered with sand and dust.