Daily Project Report
Weather: windy
Temperature: 78
Work Completed Today: Wrecked forms on Invert #1 and cleaned up debris. Tied steel in walls of Tunnel #1. El Abassy says containers are in Marrakech, will be here tomorrow. Started setting wall forms in pit. Surveyors checked tunnel #1 for location and elevation. Started to set floor forms in tunnel 3#.
Owner/Engineer directives provided: Delivered expansion joint detail to CIMAR to give to SOCOTEC for approval.
Equipment: Bought 3' level, drill bits, garden sprayer, etc.
Visitors: Mr. Chafiq, Mr. Talbi and CIMAR Safety Rep. Turned in all requested paperwork.

Mr.'s Talbi, Chafiq and Safety man from CIMAR.