Daily Project Report
Weather: Blowing Sand
Temperature: 85
Work Completed Today:
Poured invert for collection tunnel. Concrete was 2 hours late. Pump was down for 1 hour. consequently we were pouring and finishing in our daily sand/wind storm. Floor is okay. Many Visitors from Maroc Cement.

Owner/Engineer directives provided: New tunnel design with 6 " mud slab.
Other notes of interest/visitors: Mssrs. Talibi, Chafiq and others.