Weather: Nice
Temperature: 80 Degrees
Work Completed Today:
Finished tying floor steel in pit. Placed approximately 1/2 of the dowels. Began setting forms. received 1 truck of rebar. Staged rebar for tunnel #1. Was promised a meeting with representative from Betamar (redi-mix-affiliate of ICG) He didn't sow up. Fabricated more dowels. signed contract with labor provider. Rnewed lease on rental car.