Friday May 2, 2008

Daily Project Report
Weather: Warm and sunny
Temperature: 85 degrees F.
Work Completed Today:


1. Poured mud slab for pit. 56 cu. meters.
2. Excavated for mud slab on tunnel #1
3. Fabricated rebar chairs for pit invert
4. Wrecked forms on mud slab.
5. Worked on sump pit
6. Mr. Chafiq from CIMAR was very distressed that we used TGY for concrete on our mud slab instead of them. We told them we would be happy to entertain a bid from them.
7. Had a meeting with SOCOTEC & CIMAR - We have big issues
8. Reported all to office
9. Rebar price is going up
10. Unloaded 1 truck of rebar today.