Saturday, May 24, 2008

Thursday May 22, 2008

Daily Project Report
Weather: Nice in the A.M. Warm,Windy and lots of sand in the P.M.
Teperature: 85
Work Completed Today: Had inspection on tunnel #1 invert. Everything Good. M. El Hani from SOCOTEC told me we would have to have some complete expansion joints in the tunnels. Mr. Fez and the surveyors were out again. Said our collection tunnel was okay, but not exactly the correct elevation because we were using an incorrect benchmark elevation. We will pour all tunnel floors as high to stay consistent.
Did you talk to office/project manager today?: Yes
Owner Engineer directives provided: Expansion joint in all tunnels complete break including rebar, concrete, and steel lock. They want a detail from ES2.
Visitors: Mr. Chafiq, M. El Hani, Mr. Fez

Still setting elevations.

Blue Men on Tunnel #3

Tunnel #1

Tunnel #3


Our Lunch room. (And sometime's Aziz's office)

Fixing a minor burn.

Our little mascot who hangs around the job. Cody calls her "Dome" and Cindy calls her "Gitmo".



A look at both tunnels .

No comments: