Tuesday, June 3, 2008

Wednesday May 28, 2008

Daily Project Report
Weather:
Windy
Temp: 78
Work completed today: Set inside forms for wall on Tunnel #1. Unloaded containers
Owner/Engineer directives: Fez from CIMAR.
SOCOTEC inspected the invert for tunnel #3 and walls for Tunnel #1.
Equipment Delivered: Container with forms and container with Forklift arrived. 1 Truck of dowels from DAVUM. Repairing the Big hammer drill.

Unloading the forklift and putting it back together.