Weather: Sahara
Temperature: 83
Work Completed today: We poured first section of walls in collection pit. Installed wall forms for more walls in tunnel #1. Met with Chafiq and Backfill contractor. Backfill should start next week. Aziz took documents to the police station to legalize residency for crew.