Wednesday, June 4, 2008

Monday June 2, 2008

Daily Project Report
Weather: Warm and Sunny
Temperature: 85
Work completed Today: Set forms for more walls on tunnel #1. Tied Steel in collection pit walls. Met with Chafiq and Talbi. told them I was not pleased with how our floor on tunnel #3 turned out and if it wasn't acceptable I would remove it. Continued removing mud slab on tunnel #3.

Materials Delivered: #16 bar from Gilfarmer.
Visitors: Talbi and Chafiq