Tuesday, May 20, 2008

Tuesday May 20, 2008

Daily Project Report
Weather: Windy
Temperature: 82
Work Completed Today: Tied floor steel in Arch tunnel #1. Tied floor steel in Arch tunnel #3. Taught some of the Blue Men how to use twisters. Finally found some concrete pavers that we could use for dobies. Made chairs for floor steel. Tied steel in pit walls. Finally got rebar bid.
Did not talk to Project Manager/Office Today
Materials Delivered: Dobies
Visitors: ICG

I did not have any pictures from today, so I decided to show you what the trucks have to do to navigate getting in and out of the excavation.


Monday May 19, 2008

Daily Project Report
Weather:
Windy/sand
Temperature: 85 degrees
Work Completed Today:
4 new locals started today making our Blue Man Crew 12. Tied steel in pit walls. Tied steel in invert for tunnel #1. Excavated on center tunnel. Cleaned up debris from pit invert pour. Poured mud slab for arch tunnel #3.
Did you talk with Office/ project manager today?: Yes
Owner/Engineer directives provided: Yes
Equipment delivered: Forklift
Visitors: Mr.s Chafiq and Talbi


The site that greeted us first thing this morning was around twenty men wanting a job.









The pictures aren't in any certain order. We have Jeff making chairs, Darryl and help making dobies, Luis setting chairs, Cleaning up dibris, tying steel, a photographer and videographer filming the work.










Cindy making chairs and the guys starting the pour. Comparing the two fresh pours. The one in the top corner was poured an hour earlier and is covered with sand and dust.




Monday, May 19, 2008

Saturday May 17, 2008

Daily Project Report
Weather: Windy
Temperature: 82
Work Completed Today:
Lined out tunnel #1 floor on Mud slab. Tied bottom mat.

Since I don't have pictures of the work done on Saturday, I thought I would share the pictures of the fun. Aziz's son was born on the 7th of this month. On the 14th a lamb was killed for the baby and an Imam (Muslim Holy man) blessed him. We were invited to dinner on Saturday night to eat the lamb and celebrate the Baby. The baby's name is Jade. The 4 course dinner was delicious!


Friday, May 16, 2008

Friday May 16, 2008

Daily Project Report
Weather: Cool and rainy in the morning
Temperature: 76 degrees
Work Completed Today: Tied steel in collection pit walls. Started excavation on tunnel #2.
Poured mud slab for tunnel #1.
Owner/Engineer directives provided: Robert and Doug confirmed go ahead on tunnels #1 & #3.
Other Notes of Interest/visitors: Mr. Chafiq said he would talk to Betomar about concrete price. He gave us the go ahead on tunnels 1 & 3.


Without a forklift, we hand carry the bar to the tunnels.
A daily occurance is men, young and old, coming by the site to ask for a job. The most we had was around 30 in one day. Now it has slowed down to 3 -5 a day. We will have several stand outside the fence surrounding the excavation and just watch us.
Our guys and the 'Blue Man Group' working in the collection pit.
The watering truck.
The Blue Man Group Passing bar to the pit.

Mud slab pour.


Going down into the hole.
Darryl and the Dome crew.
Getting out was a bit of a challenge.

Thursday May 15, 2008

Daily Project Report
Weather: Warm
Temperature: 80 Degrees
Work Completed Today:
Tied steel in walls of collection pit. Finished forming 1st tunnel mud slab, continued excavating tunnel #3. Met with rebar supplier and forklift supplier. Paid phone bill.
Owner/Engineer directives provided: Talked to Doug and robert about questions on plans. Other notes of interest/visitors: Mr. Chafiq
The battery died on my camera, so these pictures are from yesterday.



Wednesday May 14, 2008

Daily Project Report
Weather:
The Same as Yesterday
Temperature: 83 degrees
Work Completed Today:
Layed out walls for collection pit. Tied rebar in walls. Met with Rebar Company. Tried to rent a forklift. Locals finished tunnel # 1, started on tunnel #3.



Tuesday May 13, 2998

Daily Project Report
Weather:
Warm and windy
Temperature: 83 degrees
Work Completed Today:
Tied Bar in walls of collection pit. Wrecked forms. Eight locals started working today digging the mud slab in tunnel #1.

The locals (we call them "The Blue Man Group" because they are required to wear the blue R.M.O. jumpsuit) working with Joe.