WORK COMPLETED TODAY:
Began digging out for mud slab on Tunnel #1 while watching for containers. El Abbasy says sometime tomorrow. Received new quote on crane from Carlos Moreno. Visited with Barry about rebar supplier.

The is the other company care we wanted to get, but it was not for sale. Instead we rented another little Renault.

Starting to dig out for the mud slab. The temperature is 95 degrees on the top.

It is much hotter in the hole.


Fixing the tools. This also gives you a good view of what they are digging in.

They have a ways to go.


A view of part of the security fence. Darryl and Aziz are down in the pit of despair making new measurements.