Daily Project Report
Weather: Hot and Sunny
Temperature: 95 degrees F.

Work Completed Today: Removed rock from mud slab. Visited the port to try and facilitate container release. Delivered rebar take-off to two people to bid on. Attended safety meeting at CIMAR for all contractors. Received commets from SOCOTEC on tunnel engineering. Excavators should start re-excavation on tunnel floor/ramp tomorrow. Paid day and night watchmen through today in cash because we still don't have a contract with RMO (Man-power etc.) We've lost 3 pair of shoes in the last 2 days due to soles melting off.